Architectural Blossoming of the Lotus
The temples of the Bahá'í Faith are well known for their architectural splendor, and the Temple constructed in Delhi is a continuation of this rich tradition. Before undertaking the design of the temple, the architect, Mr. Fariborz Sahba, had travelled extensively in India to study the architecture of this land and was impressed by the design of the beautiful temples, as well as by the art and religious symbols wherein the lotus invariably played an important role. He was influenced by this experience, and in an attempt to bring out the concept of purity, simplicity and freshness of the Bahá’í Faith, he conceived the Temple in Delhi in the form of a lotus. The temple gives the impression of a half-open lotus flower, afloat, surrounded by its leaves. Each component of the temple is repeated nine times. Flint & Neill Partnership of London were the consultants and the ECC Construction Group of Larsen & Toubro Limited were the contractors responsible for constructing the Temple.
The temple complex, as seen from the layout, consists of the main house of worship; the ancillary block which houses the reception centre, the library and the administrative building; and the restrooms block. The temple proper comprises a basement to accommodate the electrical and plumbing components, and a lotus-shaped superstructure to house the assembly area.
All around the lotus are walkways with beautiful curved balustrades, bridges and stairs, which surround the nine pools representing the floating leaves of the lotus. Apart from serving an obvious aesthetic function, the pools also help ventilate the building.
The lotus, as seen from outside, has three sets of leaves or petals, all of which are made out of thin concrete shells. The outermost set of nine petals, called the 'entrance leaves', open outwards and form the nine entrances all around the outer annular hall. The next set of nine petals, called the 'outer leaves', point inwards. The entrance and outer leaves together cover the outer hall. The third set of nine petals, called the 'inner leaves', appear to be partly closed. Only the tips open out, somewhat like a partly opened bud. This portion, which rises above the rest, forms the main structure housing the central hall. Near the top where the leaves separate out, nine radial beams provide the necessary lateral support. Since the lotus is open at the top, a glass and steel roof at the level of the radial beams provides protection from rain and facilitates the entry of natural light into the auditorium.
Below the entrance leaves and outer leaves, nine massive arches rise in a ring. A row of steps through each arch lead into the main hall
The inner leaves enclose the interior dome in a canopy made of crisscrossing ribs and shells of intricate pattern. When viewed from inside, each layer of ribs and shells disappears as it rises, behind the next, lower layer (see section on p. 29). Some of the ribs converge radially and meet at a central hub. The radial beams emanating from the inner leaves described earlier meet at the centre of the building and rest on this hub. A neoprene pad is provided between the radial beams and the top of the interior dome to allow lateral movement caused by the effects of temperature changes and wind
Geometry
The beautiful concept of the lotus, as conceived by the architect, had to be converted into definable geometrical shapes such as spheres, cylinders, toroids and cones. These shapes were translated into equations, which were then used as a basis for structural analysis and engineering drawings. The resultant geometry was so complex that it took the designers over two and a half years to complete the detailed drawings of the temple. An attempt is made below to describe this complex geometry in simple terms
Entrance leaves and outer leaves.
The entrance leaf is 18.2m wide at the entrance and rises 7.8m above the podium level. The outer leaf is 15.4m wide and rises up to 22.5m above the podium.
The inner leaves.
The inner leaves rise to an elevation of 34.3m above the inner podium. At the lowest level each shell has a maximum width of 14m. It is uniformly 200mm thick.
The arch.
All around the central hall are nine splendid arches placed at angular intervals of 40 degrees. The shape of these arches is formed by a number of plane, conical and cylindrical surfaces. The intersection of these surfaces provides interesting contours and greatly enhances the beauty of the arches. The nine arches bear almost the entire load of the superstructure
The interior dome.
Up to a certain height, the space between the ribs is covered by two layers of 6Omm-thick shells. The intricate pattern of the interior dome is illustrated in section on page 29.
Setting out
First, 18 radial lines were established from the centre of the building (see Fig. 4). Along these lines, using inclined and vertical distances, end points A and B for surface (1) were established. By using a set of curved templates, each of varying curvature, surface (1) between these lines was developed. From this surface the other surfaces of the arch were set out by using stepped templates with respect to surface
The stations shown in Fig. 3 were used to set out the cusp, re-entrance and edge lines for the entrance, outer and inner leaves. For example, to arrive at curve AB, point A with coordinates XA, YA, ZA was defined with respect to 0. AB was then established by a second theodolite and the curve AB determined by a stepped template. Accurately made curved templates of required radii were then used to develop the surface between these boundaries
Sequences of construction
Inner leaf, radial beams and central hub.
Interior dome.
Entrance and outer leaves.
Structure
All Bahá'í Houses of Worship, including the Lotus Temple, share certain architectural elements, some of which are specified by Bahá'í scripture. `Abdu'l-Bahá, the son of the founder of the religion, stipulated that an essential architectural character of a House of Worship is a nine-sided circular shape.While all current Bahá'í Houses of Worship have a dome, this is not regarded as an essential part of their architecture. Bahá'í scripture also states that no pictures, statues or images be displayed within the House of Worship and no pulpits or altars be incorporated as an architectural feature (readers may stand behind simple portable lecture stands).
Inspired by the lotus flower, the design for the House of Worship in New Delhi is composed of 27 free-standing marble clad "petals" arranged in clusters of three to form nine sides. The nine doors of the Lotus Temple open onto a central hall slightly more than 40 meters tall that is capable of holding up to 2,500 people. The surface of the House of Worship is made of white marble from Penteli mountain in Greece, the very same from which many ancient monuments and other Bahá'í Houses of Worship are built Along with its nine surrounding ponds and the gardens, the Lotus Temple property comprises 26 acres (105,000 m²; 10.5 ha).
The site
is in the village of Bahapur, in the National Capital Territory of Delhi. The
architect was an Iranian, who now lives in Canada, named Fariborz Sahba. He was
approached in 1976 to design it and later oversaw its construction. The major
part of the funds needed to buy this land was donated by Ardishír Rustampúr of
Hyderabad, who gave his entire life savings for this purpose in 1953.[8] A
portion of construction budget was saved and used to build a greenhouse to study
indigenous plants and flowers that would be appropriate for use on the
site.
Deflection was an important consideration in the design of the
formwork. The maximum deflection was limited to 3mm over a distance of
1m (including errors in fabrication and erection).
The following aspects were considered in arriving at
the general arrangement of the staging supporting the
inner leaf and interior dome formwork:
a. The concreting of the shells should be taken up 3 at a time, 120 deg. apart, so that the lateral loads on the staging supporting the formwork were reduced as far as possible.
b. Construction joints were to be avoided as far as possible so that the exposed concrete surface did not show any lines other than the architectural pattern. For the inner leaf, construction joints were to be located above 24.8m level so that they did not show from the floor level. All other shells were to be cast in a single continuous pour.
c. The staging should support the radial and base ribs without interfering with the structural steel members. After deshuttering of inner leaf, the structure should be able to support the formwork of the inner layers of shells of the interior dome with minimum modification.
From the above considerations, a space frame consisting of 9 radial cusp frames and 9 re-entrant frames, with circumferential and diagonal members closely following the profile of ribs and shells, was considered most suitable
Various alternatives were considered for the steel staging. Standard pipe scaffolding was found to be unsuitable, considering that the slippage of members at joints would be uncertain and it would be difficult to compute and control the deflection, particularly due to lateral loads. Structural steel framework with bolted joints was found to be unsatisfactory, considering that a very high degree of accuracy in fabrication and erection of structural work would be required to match the bolt holes at junctions of members meeting at different inclinations in all three planes. Structural steel framework with welded joints was considered to be most suitable because deflections due to slippage of joints would be avoided and fabrication and erection would be comparatively easier.
The inner surfaces of all the shells have a uniform, bush-hammered, exposed concrete surface with architectural patterns. For the inner leaves, these patterns were formed out of radial and vertical planes intersecting the surface of the torus. For the outer and entrance leaves, and the interior dome, the patterns were formed out of longitudes and latitudes of spheres. The formwork was designed in a manner that timber joists support the panels instead of the regular pattern of the structural steel supporting members of the space frame
Full-scale mockups of the bottom surface of each of the shells were first made at ground level and the architectural patterns marked on this surface. The frame of each form panel was fabricated according to calculated dimensions and cross-checked with measurements from the mockup. The formwork pattern is seen in the photograph on page 70.
The inner formwork for every petal was fully fixed from bottom to top and aligned accurately. After the formwork was approved, the sheathing joints where sealed with putty made out of epoxy resin and plaster of Paris, and a protective coating was applied over the plywood surface. In the case of the interior dome shells, the plywood sheathing was lined by fiber-reinforced plastic sheets and the joints sealed with epoxy resin. After this, the location of each reinforcement bar was marked on the formwork along latitudes and longitudes and the bars placed over the markings. To avoid impressions of cold joints on the inner surface, the casting of petals of the inner leaf was carried out in three lifts, some of them 14m high. To facilitate placement of concrete and simultaneous compaction in each pour, the outer formwork was placed one row of panels at a time, and as the level of concrete rose, the next row of panels was fixed. These panels, therefore, had to be fixed in position and aligned accurately in the shortest possible time.
Through selected points matching with the architectural pattern, pipe supports were taken from the inner leaf staging. These pipes supported a structural steel grid closely following the profile of the outer surface of the shells. The grid supported the outer formwork against the concrete pressure and also accommodated the working platforms at all levels. Through-ties connecting the inner and outer forms were provided at selected points so as to reduce the load on the steel staging and limit the deflection of formwork.
The longitudinal support members of the backform had accurately aligned shaped members, such that when the backform panels were placed in position and wedged, the outer surface of the shell was attained without further alignment (see Fig. 9). To ensure that the panels fitted exactly between the shaped members and there was no delay, the fixing of the panels for the entire shell was carried out in advance.
The following loads were considered for the design of the formwork:
I. Dead load of formwork - 750 N/m2 of surface area.
II. Self-weight of structural steel members.
III. Live load 2000 N/m2 of plan area.
IV. The greater of dead load of concrete (or) liquid pressure at any point corresponding to the rate of placement 0.45 m/hr and minimum temperature of 10 deg. C (during winter). Concrete pressure was calculated as per ACI publication - SP.4. Liquid pressure p = 7.2 + ([785R]/[Tc + 17.8]) P = Lateral liquid pressure - KN/m2 R = Rate of placement — m/hr Tc= Temperature of concrete in the forms deg. C
V. Basic wind pressure = 1000 N/m2
For the inner leaf, various combinations of the above loads were considered for the following conditions
Stage I Concrete from top of arch to +24.8m level Stage II Concrete from +24.8m to +38m level Stage III Concrete from +38.8m to the top
The combination of loads considered were:
1. Self-weight of space frame (symmetrical)
2. Dead load of shutter
3. Live load + dead load of concrete Stage I (unsymmetrical)
4. Live load + dead load of concrete Stage I (symmetrical)
5. Live load + dead load of concrete Stage II (unsymmetrical)
6. Live load + dead load of concrete Stage II (symmetrical)
7. Live load + dead load of concrete Stage III (unsymmetrical)
8. Live load + dead load of concrete Stage III (symmetrical)
9. Wind load for full height (unsymmetrical)
Based on the above loads, a computer analysis for all possible combinations was carried out using SAP IV program. One cusp frame and one re-entrant frame along with inter-connecting bracings were considered as a unit.
Similar loading conditions were considered for the entrance and outer leaves as also the shells of the interior dome, the only difference being that all the shells were cast in a single pour.
The
reinforcement used in the white concrete shells as well as the binding
wires was entirely galvanized so as to prevent the long-term effect of
rusting of reinforcement on the white concrete. Since galvanized
reinforcement for concrete is seldom used in this country, several tests
were carried out to ensure that the mechanical properties of
reinforcement did not become adversely affected due to galvanizing.
Sandblasting was carried out to reduce pickling time with a view to
avoiding hydrogen embrittlement. The bottom formwork for one shell for
each of the leaves was first erected and aligned. The edge lines and
surfaces of this formwork were then used as a mockup to decide the
length and shape of each bar in the shell. To avoid the impression of
cover blocks on the exposed surface of the shells, the inner layer of
reinforcement was held in position by special steel spacers supported
from the outer formwork.
All the ribs and shells up to radial beam level are in white
concrete. To avoid crazing and shrinkage cracks, a mix of M 30 grade
white concrete was designed considering that the cement content should
be below 500 kg/m3 and the quantity of water reduced to a minimum.
Tests carried out on Indian cement revealed that the strength and other properties varied considerably and the colour did not meet the architectural requirement. Trial mixes also showed a higher cement requirement of 430-450 kg/m3. The entire quantity of white cement was therefore imported from Korea. With the imported cement, it was possible to produce concrete having 28 days cube strength of 55-60 N/mm2 with a cement content of 380 to 400 Kg/m3. A mix of 1:1.44:3.36 and w/c ratio of .42 was adopted. To achieve a high workability, slump 1-120 mm, super plasticiser, .5 to .75% by weight of cement was used.
Specially graded dolomite aggregates were procured from the Alwar mines near Delhi and white silica sand from Jaipur. The maximum temperature of concrete at the time of placing was limited to 30 deg. C. During the summer months, when the ambient temperature was as high as 45 deg. C, the temperature of the concrete was controlled by adding a measured quantity of ice and by the precooling of aggregates in air-cooled aggregate storage bins. To avoid cold joints due to stoppage of work during heavy rains, as also to protect rain water entering the forms, the entire concreting area was covered by tarpaulins.
After removal of the outer forms, the surface of the concrete was covered with hessian and cured for 28 days by keeping it wet continuously by a sprinkler arrangement fixed at the top of the shells.
The shells of the interior dome were initially 50mm thick and
proposed to be cast by in-situ guniting. Full-scale mockups were used to
study the problems of working space and accessibility, and it was felt
that due to limited space available between the shells, the working
conditions for guniting operations would be difficult. As an
alternative, the shells were therefore proposed to be constructed in
in-situ concrete using formwork on both faces. Considering that each
shell had to be cast in a single pour, the fixing of formwork and
reinforcement, as also the placement and compaction of concrete between
two faces of formwork only 60 mm apart, posed serious problems. Not only
was the formwork difficult to align so as to accurately produce the
complex, doubly curved surface and the intersections, but also the
closeness of the petals, one fold behind the next, caused serious
problems of work space for fixing formwork, reinforcement and
concreting.
Based on the sequence of construction envisaged, the assumptions made
in the design of the formwork, the procedures developed from mockups,
and the tests carried out on materials, detailed method statements and
criteria of acceptance were established. Checking of workmanship was
done at each stage to produce the required quality and accuracy and also
to ensure that there was no deviation from the conditions of loading
assumed in the design of the formwork. A full-fledged concrete
laboratory carried out mix designs for different grades of concrete and
exercised strict control on the quality of concrete.
The outer surface of the shells, as also the inner surface of the
arches, are cladded with white marble panels fixed to the concrete
surface with specially designed stainless steel brackets and anchors.
10,000 sq.m. of marble was quarried from the Mount Pentilekon mines of
Greece and thereafter sent to Italy, where each panel was cut to the
required size and shape to suit the geometry and architectural pattern
before transporting them to the site in Delhi.
After waterproofing of the top surface of each shell, timber templates of the same size as the marble panels were used to define the location of the bottom-most rows of marble panels first. The geometry of the cusp re-entrant and edge lines was then accurately checked with respect to these panels, and the marble pieces were fixed in position from bottom towards top and cusp towards reentrants and edges. Edge holes were drilled at ground level for each marble panel before the panels were placed in position. Holes were drilled in the concrete to accommodate the anchor fasteners of the stainless steel brackets to suit the holes in the marble, after each panel was aligned. After fixing of the brackets, the area around the bracket hole was sealed with a special waterproofing compound
The alignment of the panels was adjusted at each layer so that the surface geometry and pattern lines were maintained. The pieces near edge, re-entrant and cusp lines were cut to suit the boundary lines. Gaps 8 to 10 mm wide at the joints were filled with moulded rubber cordon, and the top of the joints, as also the holes in the marble, sealed with silicon sealant. The entire marble surface was, lastly, washed with a solution of 30% muriartic acid mixed in water, to remove dirt and stains.
A specially designed structural steel framework was provided to accommodate access and working platforms. The platforms were free from the surface of the shells so that the marble fixing could be carried out without any hindrance from the supports of the staging.
It may be interesting to note that all the marble work was carried out by carpenters who learned the skill of marble fixing within a few weeks, and were able to complete the work, to the required accuracy, two months ahead of the scheduled completion time.
The complexity of the structure, and the very high standards of
workmanship expected to be achieved, demanded a dynamic construction
management with a high degree of innovativeness, team spirit and quality
consciousness on the part of staff and workmen. Anticipating problems
in advance and solving them through trials and mockups was an essential
part of site planning. Further, great emphasis was laid on the
completion of the project within the stipulated time and cost. Resources
were planned and physical progress monitored through constant review of
PERT/CPM networks.
Video :
Staging and formwork
The following aspects were considered in arriving at
the general arrangement of the staging supporting the
inner leaf and interior dome formwork:
a. The concreting of the shells should be taken up 3 at a time, 120 deg. apart, so that the lateral loads on the staging supporting the formwork were reduced as far as possible.
b. Construction joints were to be avoided as far as possible so that the exposed concrete surface did not show any lines other than the architectural pattern. For the inner leaf, construction joints were to be located above 24.8m level so that they did not show from the floor level. All other shells were to be cast in a single continuous pour.
c. The staging should support the radial and base ribs without interfering with the structural steel members. After deshuttering of inner leaf, the structure should be able to support the formwork of the inner layers of shells of the interior dome with minimum modification.
From the above considerations, a space frame consisting of 9 radial cusp frames and 9 re-entrant frames, with circumferential and diagonal members closely following the profile of ribs and shells, was considered most suitable
Various alternatives were considered for the steel staging. Standard pipe scaffolding was found to be unsuitable, considering that the slippage of members at joints would be uncertain and it would be difficult to compute and control the deflection, particularly due to lateral loads. Structural steel framework with bolted joints was found to be unsatisfactory, considering that a very high degree of accuracy in fabrication and erection of structural work would be required to match the bolt holes at junctions of members meeting at different inclinations in all three planes. Structural steel framework with welded joints was considered to be most suitable because deflections due to slippage of joints would be avoided and fabrication and erection would be comparatively easier.
The inner surfaces of all the shells have a uniform, bush-hammered, exposed concrete surface with architectural patterns. For the inner leaves, these patterns were formed out of radial and vertical planes intersecting the surface of the torus. For the outer and entrance leaves, and the interior dome, the patterns were formed out of longitudes and latitudes of spheres. The formwork was designed in a manner that timber joists support the panels instead of the regular pattern of the structural steel supporting members of the space frame
Full-scale mockups of the bottom surface of each of the shells were first made at ground level and the architectural patterns marked on this surface. The frame of each form panel was fabricated according to calculated dimensions and cross-checked with measurements from the mockup. The formwork pattern is seen in the photograph on page 70.
The inner formwork for every petal was fully fixed from bottom to top and aligned accurately. After the formwork was approved, the sheathing joints where sealed with putty made out of epoxy resin and plaster of Paris, and a protective coating was applied over the plywood surface. In the case of the interior dome shells, the plywood sheathing was lined by fiber-reinforced plastic sheets and the joints sealed with epoxy resin. After this, the location of each reinforcement bar was marked on the formwork along latitudes and longitudes and the bars placed over the markings. To avoid impressions of cold joints on the inner surface, the casting of petals of the inner leaf was carried out in three lifts, some of them 14m high. To facilitate placement of concrete and simultaneous compaction in each pour, the outer formwork was placed one row of panels at a time, and as the level of concrete rose, the next row of panels was fixed. These panels, therefore, had to be fixed in position and aligned accurately in the shortest possible time.
Through selected points matching with the architectural pattern, pipe supports were taken from the inner leaf staging. These pipes supported a structural steel grid closely following the profile of the outer surface of the shells. The grid supported the outer formwork against the concrete pressure and also accommodated the working platforms at all levels. Through-ties connecting the inner and outer forms were provided at selected points so as to reduce the load on the steel staging and limit the deflection of formwork.
The longitudinal support members of the backform had accurately aligned shaped members, such that when the backform panels were placed in position and wedged, the outer surface of the shell was attained without further alignment (see Fig. 9). To ensure that the panels fitted exactly between the shaped members and there was no delay, the fixing of the panels for the entire shell was carried out in advance.
Loading
I. Dead load of formwork - 750 N/m2 of surface area.
II. Self-weight of structural steel members.
III. Live load 2000 N/m2 of plan area.
IV. The greater of dead load of concrete (or) liquid pressure at any point corresponding to the rate of placement 0.45 m/hr and minimum temperature of 10 deg. C (during winter). Concrete pressure was calculated as per ACI publication - SP.4. Liquid pressure p = 7.2 + ([785R]/[Tc + 17.8]) P = Lateral liquid pressure - KN/m2 R = Rate of placement — m/hr Tc= Temperature of concrete in the forms deg. C
V. Basic wind pressure = 1000 N/m2
For the inner leaf, various combinations of the above loads were considered for the following conditions
Stage I Concrete from top of arch to +24.8m level Stage II Concrete from +24.8m to +38m level Stage III Concrete from +38.8m to the top
The combination of loads considered were:
1. Self-weight of space frame (symmetrical)
2. Dead load of shutter
3. Live load + dead load of concrete Stage I (unsymmetrical)
4. Live load + dead load of concrete Stage I (symmetrical)
5. Live load + dead load of concrete Stage II (unsymmetrical)
6. Live load + dead load of concrete Stage II (symmetrical)
7. Live load + dead load of concrete Stage III (unsymmetrical)
8. Live load + dead load of concrete Stage III (symmetrical)
9. Wind load for full height (unsymmetrical)
Based on the above loads, a computer analysis for all possible combinations was carried out using SAP IV program. One cusp frame and one re-entrant frame along with inter-connecting bracings were considered as a unit.
Similar loading conditions were considered for the entrance and outer leaves as also the shells of the interior dome, the only difference being that all the shells were cast in a single pour.
Reinforcement
Concrete
Tests carried out on Indian cement revealed that the strength and other properties varied considerably and the colour did not meet the architectural requirement. Trial mixes also showed a higher cement requirement of 430-450 kg/m3. The entire quantity of white cement was therefore imported from Korea. With the imported cement, it was possible to produce concrete having 28 days cube strength of 55-60 N/mm2 with a cement content of 380 to 400 Kg/m3. A mix of 1:1.44:3.36 and w/c ratio of .42 was adopted. To achieve a high workability, slump 1-120 mm, super plasticiser, .5 to .75% by weight of cement was used.
Specially graded dolomite aggregates were procured from the Alwar mines near Delhi and white silica sand from Jaipur. The maximum temperature of concrete at the time of placing was limited to 30 deg. C. During the summer months, when the ambient temperature was as high as 45 deg. C, the temperature of the concrete was controlled by adding a measured quantity of ice and by the precooling of aggregates in air-cooled aggregate storage bins. To avoid cold joints due to stoppage of work during heavy rains, as also to protect rain water entering the forms, the entire concreting area was covered by tarpaulins.
After removal of the outer forms, the surface of the concrete was covered with hessian and cured for 28 days by keeping it wet continuously by a sprinkler arrangement fixed at the top of the shells.
Trials and mockups
Quality assurance
Marble cladding
After waterproofing of the top surface of each shell, timber templates of the same size as the marble panels were used to define the location of the bottom-most rows of marble panels first. The geometry of the cusp re-entrant and edge lines was then accurately checked with respect to these panels, and the marble pieces were fixed in position from bottom towards top and cusp towards reentrants and edges. Edge holes were drilled at ground level for each marble panel before the panels were placed in position. Holes were drilled in the concrete to accommodate the anchor fasteners of the stainless steel brackets to suit the holes in the marble, after each panel was aligned. After fixing of the brackets, the area around the bracket hole was sealed with a special waterproofing compound
The alignment of the panels was adjusted at each layer so that the surface geometry and pattern lines were maintained. The pieces near edge, re-entrant and cusp lines were cut to suit the boundary lines. Gaps 8 to 10 mm wide at the joints were filled with moulded rubber cordon, and the top of the joints, as also the holes in the marble, sealed with silicon sealant. The entire marble surface was, lastly, washed with a solution of 30% muriartic acid mixed in water, to remove dirt and stains.
A specially designed structural steel framework was provided to accommodate access and working platforms. The platforms were free from the surface of the shells so that the marble fixing could be carried out without any hindrance from the supports of the staging.
It may be interesting to note that all the marble work was carried out by carpenters who learned the skill of marble fixing within a few weeks, and were able to complete the work, to the required accuracy, two months ahead of the scheduled completion time.
Project management